Book an appointment with us, or search the directory to find the right lawyer for you directly through the app.
Find out moreThis special edition of Law Update, marking Al Tamimi & Company’s 35th anniversary, explores the evolving legal landscape of energy and climate law across the region.
As the Middle East prioritises sustainable growth, this edition examines key developments shaping the future of the sector. From the UAE’s Federal Law No. 11 of 2024 to advancements in green hydrogen, solar financing, and carbon capture technology, we spotlight the innovative strides and challenges defining this critical area.
We also go into Saudi Arabia’s initiatives to integrate carbon capture into its industrial expansion and Egypt’s AFRICARBONEX platform, which underscores the region’s commitment to a sustainable and inclusive future.
Join us as we celebrate 35 years of legal excellence and forward-thinking insights, paving the way for a more sustainable tomorrow.
Read NowKhaled Gamaleldeen - Senior Counsel - Litigation
Marwa El Mahdy
February 2014
The doctrine of anticipatory breach is found in English common law. It holds that if, before performance is due, a party expresses an intention to break the contract by not performing (or otherwise acts in such a way to lead a reasonable person to the conclusion that the party does not intend to perform), then this is an “anticipatory breach” and entitles the other party to accept the repudiation and seek damages immediately, or wait until performance is due and then seek damages for the failure to perform.
No similar doctrine is known to exist under UAE law, but a recent Dubai Court of Cassation judgment appears to confirm a recent trend by the courts to create a similar doctrine for off-plan real estate disputes. In Dubai Court of Cassation judgment 200/2013 (Real Estate Appeal) the court decided that a buyer may legitimately withhold the performance of his due obligation (to price), if there are serious reasons to lead the purchaser to believe that developer, though presently not in breach, will fail to perform his future obligation (to deliver the unit on time).
Facts of the case:
An individual purchased an off-plan real estate unit from a developer in a real estate project. It was agreed between the parties that the expected date for handing over the unit to the buyer was by 31 March 2010.
In due course the buyer paid 58.5% of the unit’s purchase price in accordance with the payment schedule, but stopped paying the installments when it appeared that the project would not be completed on time. Upon request from the developer, the Land Department sent a notice to the buyer warning the buyer that a failure to pay the instalments would result in the termination of the agreement. The buyer continued to withhold payment, and Land Department proceeded to terminate the sale agreement and allow the developer to deduct 40% of the paid amount (as per Law no. 13 of 2008).
The developer eventually failed to deliver the purchased unit at the due time, and the buyer initiated legal action before the Dubai Court of First Instance seeking a court order against the developer to cancel the agreement and refund the paid amount along with interest.
Court of First Instance and Court of Appeal
Before the Court of First Instance, the developer submitted that the percentage of completed works was 68% and that the delay was a result of force majeure. The Court of First Instance accepted this and dismissed the case.
The buyer then appealed to the Dubai Court of Appeal which appointed an engineering expert. In light of the findings of the expert’s report, the Appeal Court overturned the lower court’s decision and cancelled the agreement, ordering the developer to refund the amount paid by the Buyer with interest.
The developer then challenged the Appeal Court’s decision before the Dubai Court of Cassation.
Developer’s grounds for appeal:
The developer submitted that the Appeal Court erred in its decision for the following reasons:
The Court of Cassation:
The Cassation Court dismissed the developer’s arguments and held:
Practice Note:
The above decision is representative of a recent change in approach by the Dubai Court of Cassation in recent real estate cases. Whilst the Civil Code is clear that one party can refuse to perform if the other party has stopped (Article 247), the new approach appears to allow a party to withhold performance even when the other party still performing, provided there are ‘serious reasons’ that have led the party to believe that the other party will not perform its future obligations. This is similar too the English common-law doctrine of anticipatory breach.
This new approach must however be followed with the utmost caution
The “serious reasons” that led to the withholding of performance are subject to the discretionary power of the court, and will not be upheld unless the withholding party can prove that the reasons are sufficiently serious. It is still not clear what will be considered “serious reasons”, though in Dubai Court of Cassation (in case 179 of 2012) the court held that failure by a developer to start construction within six months of receiving approval to sell the units off-plan might be sufficient.
What can be said is that if a buyer chooses to withhold payment due to fears about the developer’s ability to deliver the unit on time, the buyer must ensure it has clear and compelling evidence to show that the fears are well founded at the time the decision to withhold payment is made. Withholding performance is a serious step to take and will likely lead to the developer terminating the agreement and reselling the unit. If by the time the dispute reaches the court the project has indeed been constructed (even if delayed), it will be difficult for the buyer to maintain a case that there were serious reasons to believe the developer would not perform.